Architect's rendering
75,731-square-foot building
To be located across from the Administration Building on Ehle Drive
Total Project Budget: $24,009,268
Design Team:
Architect – Pearce Brinkley Cease + Lee of Raleigh
Library Consultant – Design Lab Architects of Boston
Civil – Allied Design
Structural – LHC Structural Engineers
Mechanical, Electrical, Plumbing + Fire Protection – Stanford White
Landscape – Lappas + Havener
Audio/Visual – Thornburn Associates
Interior Design – Perkins + Will
Schedule:
Early Site Package
Contractor – BECO Inc.
Construction Start May 2012
Construction Finish August 2012
Building Construction
Contractor Bidding October 2012
Construction Start November 2012 (estimated)
Construction Finish January 2014 (estimated)
Associated Projects:
Ehle Street and Parking Lighting
Contractor – BECO Inc.
Construction Start February 2012
Construction Finish August 2012
Duke Energy Utility Relocation
Contractor – Duke Energy (Pike Electric)
Construction Start April 2012
Construction Finish November 2012 (estimated to remove poles)
AT&T , Time Warner Cable, City of Winston-Salem, N.C. Department of Transportation Utility Relocation/Signal Cable
Contractor – AT&T, Time Warner, City of WS, NC DOT
Construction Start May 2012
Construction Finish October 2012 (estimated)
Pedestrian Accessible Path/Walks
Contractor – Alan Barber Concrete
Construction Start April 2012
Construction Finish April 2012
Temporary Construction Fence
Contractor – Fence Builders
Construction Start April 2012
Construction Finish May 2012
|